Class Tsk
Namespace: Aspose.Tasks
Assembly: Aspose.Tasks.dll (25.8.0)
Represents properties of Aspose.Tasks.Task object.
public static class TskInheritance
Inherited Members
object.GetType() , object.MemberwiseClone() , object.ToString() , object.Equals(object?) , object.Equals(object?, object?) , object.ReferenceEquals(object?, object?) , object.GetHashCode()
Fields
ACWP
Costs incurred for work already done on a task, up to the project status date or today’s date.
public static readonly Key<double, taskkey=""> ACWPField Value
ActivityId
Represents activity id field - a task’s unique identifier used by Primavera. (only applicable to Primavera projects).
public static readonly Key<string, taskkey=""> ActivityIdField Value
ActualCost
Costs incurred for work already performed by resources on their tasks, together with any other recorded costs associated with the task.
public static readonly Key<decimal, taskkey=""> ActualCostField Value
ActualDuration
The span of actual working time for a task, based on the scheduled duration and current remaining work or percent complete.
public static readonly Key<duration, taskkey=""> ActualDurationField Value
ActualFinish
The date when a task was completed.
public static readonly Key<datetime, taskkey=""> ActualFinishField Value
ActualOvertimeCost
Costs incurred for overtime work already performed on tasks by assigned resources.
public static readonly Key<decimal, taskkey=""> ActualOvertimeCostField Value
ActualOvertimeWork
The actual amount of overtime work already performed by resources assigned to tasks.
public static readonly Key<duration, taskkey=""> ActualOvertimeWorkField Value
ActualOvertimeWorkProtected
The duration through which actual overtime work is protected.
public static readonly Key<duration, taskkey=""> ActualOvertimeWorkProtectedField Value
ActualStart
The date and time that a task actually began.
public static readonly Key<datetime, taskkey=""> ActualStartField Value
ActualWork
The amount of work that has already been done by resources assigned to tasks.
public static readonly Key<duration, taskkey=""> ActualWorkField Value
ActualWorkProtected
The duration through which actual work is protected.
public static readonly Key<duration, taskkey=""> ActualWorkProtectedField Value
BCWP
The cumulative value of the task’s percent complete multiplied by the time phased baseline costs.
public static readonly Key<double, taskkey=""> BCWPField Value
BCWS
The cumulative time phased baseline costs up to the status date or today’s date.
public static readonly Key<double, taskkey=""> BCWSField Value
BudgetCost
Budget costs for budget cost resources. Budget resources are assigned only to the project summary task.
public static readonly Key<decimal, taskkey=""> BudgetCostField Value
BudgetWork
Budget work for budget work and material resources. Budget resources are assigned only to the project summary task.
public static readonly Key<duration, taskkey=""> BudgetWorkField Value
CV
The difference between the baseline cost and total cost for a task. Cost Variance = Cost - Baseline Cost
public static readonly Key<double, taskkey=""> CVField Value
Calendar
The task calendar.
public static readonly Key<calendar, taskkey=""> CalendarField Value
CommitmentFinish
The finish date of a delivery.
public static readonly Key<datetime, taskkey=""> CommitmentFinishField Value
CommitmentStart
The start date of a delivery.
public static readonly Key<datetime, taskkey=""> CommitmentStartField Value
CommitmentType
Determines whether a task has an associated delivery or
a dependency on an associated delivery.
public static readonly Key<int, taskkey=""> CommitmentTypeField Value
ConstraintDate
The specific date associated with the constraint type.
public static readonly Key<datetime, taskkey=""> ConstraintDateField Value
ConstraintType
Provides choices for the type of constraint that can be applied for scheduling a task.
public static readonly Key<constrainttype, taskkey=""> ConstraintTypeField Value
Key < ConstraintType , TaskKey >
Contact
The name of an individual responsible for a task.
public static readonly Key<string, taskkey=""> ContactField Value
Cost
The total scheduled or projected cost for a task based on costs already incurred for work performed by resources assigned to the tasks, in addition to the costs planned for the remaining work.
public static readonly Key<decimal, taskkey=""> CostField Value
CostVariance
The difference between the baseline cost and total cost for a task, resource, or assignment.
public static readonly Key<double, taskkey=""> CostVarianceField Value
Created
The date when a task was created.
public static readonly Key<datetime, taskkey=""> CreatedField Value
Deadline
A target date that indicates when a task is to be completed.
public static readonly Key<datetime, taskkey=""> DeadlineField Value
DisplayAsSummary
Determines whether the task should be displayed as a summary task.
public static readonly Key<nullablebool, taskkey=""> DisplayAsSummaryField Value
Key < NullableBool , TaskKey >
DisplayOnTimeline
Specifies whether a task should be displayed on a timeline view.
public static readonly Key<bool, taskkey=""> DisplayOnTimelineField Value
Duration
The total span of active working time for a task as entered or as calculated by Microsoft Project based on start date, finish date, calendars, and other scheduling factors.
public static readonly Key<duration, taskkey=""> DurationField Value
DurationText
Returns the task’s duration text.
public static readonly Key<string, taskkey=""> DurationTextField Value
DurationVariance
The difference between the baseline duration of a task and the total duration (current estimate) of a task.
public static readonly Key<duration, taskkey=""> DurationVarianceField Value
EarlyFinish
The earliest date that a task could possibly finish, based on early finish dates of predecessor and successor tasks, other constraints, and any leveling delay.
public static readonly Key<datetime, taskkey=""> EarlyFinishField Value
EarlyStart
The earliest date that a task could possibly begin, based on the early start dates of predecessor and successor tasks and other constraints.
public static readonly Key<datetime, taskkey=""> EarlyStartField Value
EarnedValueMethod
Determines whether the % Complete or Physical % Complete field should be used to calculate budgeted cost of work performed (BCWP).
public static readonly Key<earnedvaluemethodtype, taskkey=""> EarnedValueMethodField Value
Key < EarnedValueMethodType , TaskKey >
ExternalId
If a task is an external task it contains the task’s external Id.
public static readonly Key<int, taskkey=""> ExternalIdField Value
ExternalTaskProject
The source location and task identifier of an external task.
public static readonly Key<string, taskkey=""> ExternalTaskProjectField Value
ExternalUid
Contains the external task’s Unique identifier when the task is external.
public static readonly Key<int, taskkey=""> ExternalUidField Value
Finish
The scheduled finish date of a task.
public static readonly Key<datetime, taskkey=""> FinishField Value
FinishSlackTimeSpan
The duration between the Early Finish and Late Finish dates.
public static readonly Key<timespan, taskkey=""> FinishSlackTimeSpanField Value
FinishText
Returns the task’s finish text.
public static readonly Key<string, taskkey=""> FinishTextField Value
FinishVariance
The time that represents the difference between the baseline finish date of a task or assignment and its current finish date.
public static readonly Key<duration, taskkey=""> FinishVarianceField Value
FixedCost
Shows any non resource task expense.
public static readonly Key<double, taskkey=""> FixedCostField Value
FixedCostAccrual
Determines choices for how and when fixed costs are to be charged, or accrued, to the cost of a task.
public static readonly Key<costaccrualtype, taskkey=""> FixedCostAccrualField Value
Key < CostAccrualType , TaskKey >
FreeSlackTimeSpan
The time that a task can be delayed without delaying any successor tasks.
public static readonly Key<timespan, taskkey=""> FreeSlackTimeSpanField Value
Guid
The generated unique identification codes for a task.
public static readonly Key<string, taskkey=""> GuidField Value
HasOverallocatedResource
Indicates whether the task has an resource assigned which has more work on assigned tasks than can be completed within normal working capacity.
public static readonly Key<nullablebool, taskkey=""> HasOverallocatedResourceField Value
Key < NullableBool , TaskKey >
HideBar
Determines whether the Gantt bar of a task is hidden when displayed in Microsoft Project.
public static readonly Key<nullablebool, taskkey=""> HideBarField Value
Key < NullableBool , TaskKey >
Hyperlink
The title or explanatory text for a hyperlink associated with a task.
public static readonly Key<string, taskkey=""> HyperlinkField Value
HyperlinkAddress
The address for a hyperlink associated with a task.
public static readonly Key<string, taskkey=""> HyperlinkAddressField Value
Remarks
The full address (Hyperlink Href in Microsoft Project) of the hyperlink is a concatenation of HyperlinkAddress and HyperlinkSubAddress.
HyperlinkSubAddress
The specific location in a document in a hyperlink associated with a task.
public static readonly Key<string, taskkey=""> HyperlinkSubAddressField Value
Remarks
The full address (Hyperlink Href in Microsoft Project) of the hyperlink is a concatenation of HyperlinkAddress and HyperlinkSubAddress.
Id
The position identifier of a task within the list of tasks.
public static readonly Key<int, taskkey=""> IdField Value
IgnoreResourceCalendar
Determines whether the scheduling of the task considers the calendars of the resources assigned to the task.
public static readonly Key<nullablebool, taskkey=""> IgnoreResourceCalendarField Value
Key < NullableBool , TaskKey >
IgnoreWarnings
Indicates whether to hide the schedule conflict warning indicator in Microsoft Project.
public static readonly Key<bool, taskkey=""> IgnoreWarningsField Value
IsActive
Determines whether a task is active. Inactive tasks no longer affect other tasks or the overall Project schedule.
public static readonly Key<nullablebool, taskkey=""> IsActiveField Value
Key < NullableBool , TaskKey >
IsCritical
Determines whether a task is on the critical path.
public static readonly Key<nullablebool, taskkey=""> IsCriticalField Value
Key < NullableBool , TaskKey >
IsEffortDriven
Determines whether the scheduling for the task is effort-driven scheduling.
public static readonly Key<nullablebool, taskkey=""> IsEffortDrivenField Value
Key < NullableBool , TaskKey >
IsEstimated
Determines whether a task is estimated.
public static readonly Key<nullablebool, taskkey=""> IsEstimatedField Value
Key < NullableBool , TaskKey >
IsExpanded
Determines whether a summary task is expanded or not in GanttChart view.
public static readonly Key<nullablebool, taskkey=""> IsExpandedField Value
Key < NullableBool , TaskKey >
IsExternalTask
Determines whether a task is external.
public static readonly Key<bool, taskkey=""> IsExternalTaskField Value
IsManual
Determines whether a task is manually scheduled.
public static readonly Key<nullablebool, taskkey=""> IsManualField Value
Key < NullableBool , TaskKey >
IsMarked
Shows whether a task is marked for further action or identification of some kind.
public static readonly Key<bool, taskkey=""> IsMarkedField Value
Remarks
Applies to mpp file format only.
IsMilestone
Determines whether a task is a milestone.
public static readonly Key<nullablebool, taskkey=""> IsMilestoneField Value
Key < NullableBool , TaskKey >
IsNull
Determines whether a task is a null task.
public static readonly Key<nullablebool, taskkey=""> IsNullField Value
Key < NullableBool , TaskKey >
IsOverallocated
Indicates whether any of the assigned resources on a task is assigned to more work on the task than can be done withing the normal working capacity.
public static readonly Key<nullablebool, taskkey=""> IsOverallocatedField Value
Key < NullableBool , TaskKey >
IsPublished
Determines whether the current task should be published to Project Server with the rest of the project.
public static readonly Key<nullablebool, taskkey=""> IsPublishedField Value
Key < NullableBool , TaskKey >
IsRecurring
Determines whether a task is part of a series of recurring tasks.
public static readonly Key<nullablebool, taskkey=""> IsRecurringField Value
Key < NullableBool , TaskKey >
IsResumeValid
Determines whether a task can be resumed.
public static readonly Key<nullablebool, taskkey=""> IsResumeValidField Value
Key < NullableBool , TaskKey >
IsRollup
Determines whether information about the subtask Gantt bars will be rolled up to the summary task bar.
public static readonly Key<nullablebool, taskkey=""> IsRollupField Value
Key < NullableBool , TaskKey >
IsSubproject
Determines whether a task is an inserted project.
public static readonly Key<bool, taskkey=""> IsSubprojectField Value
IsSubprojectReadOnly
Determines whether a subproject is read-only.
public static readonly Key<nullablebool, taskkey=""> IsSubprojectReadOnlyField Value
Key < NullableBool , TaskKey >
IsSummary
Determines whether a task is a summary task.
public static readonly Key<bool, taskkey=""> IsSummaryField Value
LateFinish
The latest date that a task can finish without delaying the finish of the project.
public static readonly Key<datetime, taskkey=""> LateFinishField Value
LateStart
The latest date that a task can start without delaying the finish of the project.
public static readonly Key<datetime, taskkey=""> LateStartField Value
LevelAssignments
Determines whether the leveling function can delay and split individual assignments in order to resolve over allocations.
public static readonly Key<nullablebool, taskkey=""> LevelAssignmentsField Value
Key < NullableBool , TaskKey >
LevelingCanSplit
Determines whether the resource leveling function can cause splits on remaining work on this task.
public static readonly Key<nullablebool, taskkey=""> LevelingCanSplitField Value
Key < NullableBool , TaskKey >
LevelingDelay
The time that a task is to be delayed from its early start date because of resource leveling.
public static readonly Key<duration, taskkey=""> LevelingDelayField Value
ManualDuration
Defines manually scheduled duration of a task.
public static readonly Key<duration, taskkey=""> ManualDurationField Value
ManualFinish
Defines manually scheduled finish of a task.
public static readonly Key<datetime, taskkey=""> ManualFinishField Value
ManualStart
Defines manually scheduled start of a task.
public static readonly Key<datetime, taskkey=""> ManualStartField Value
Name
A task’s name.
public static readonly Key<string, taskkey=""> NameField Value
NotesRTF
The text notes in RTF format.
public static readonly Key<string, taskkey=""> NotesRTFField Value
NotesText
Notes’ plain text extracted from RTF data.
public static readonly Key<string, taskkey=""> NotesTextField Value
OutlineLevel
The outline level of a task.
public static readonly Key<int, taskkey=""> OutlineLevelField Value
OutlineNumber
The number that represents a task’s position in the hierarchical outline structure.
public static readonly Key<string, taskkey=""> OutlineNumberField Value
OvertimeCost
The total overtime cost for a task, for a resource on all assigned tasks, or for a resource assignment.
public static readonly Key<decimal, taskkey=""> OvertimeCostField Value
OvertimeWork
The amount of overtime scheduled to be performed by all resources assigned to a task.
public static readonly Key<duration, taskkey=""> OvertimeWorkField Value
PercentComplete
The current status of a task, expressed as the percentage of the task’s duration that has been completed.
public static readonly Key<int, taskkey=""> PercentCompleteField Value
PercentWorkComplete
The current status of a task expressed as the percentage of work that has been completed.
public static readonly Key<int, taskkey=""> PercentWorkCompleteField Value
PhysicalPercentComplete
Percent complete value that can be be used as an alternative for calculating budgeted cost of work performed (BCWP).
public static readonly Key<int, taskkey=""> PhysicalPercentCompleteField Value
PreleveledFinish
The finish date of a task as it was before resource leveling was done.
public static readonly Key<datetime, taskkey=""> PreleveledFinishField Value
PreleveledStart
The start date of a task as it was before resource leveling was done.
public static readonly Key<datetime, taskkey=""> PreleveledStartField Value
Priority
The level of importance given to a task, which in turn indicates how readily a task or assignment can be delayed or split during resource leveling.
public static readonly Key<int, taskkey=""> PriorityField Value
RegularWork
The total amount of non overtime work scheduled to be performed by resources.
public static readonly Key<duration, taskkey=""> RegularWorkField Value
RemainingCost
The remaining scheduled expense that will be incurred in completing the remaining scheduled work.
public static readonly Key<decimal, taskkey=""> RemainingCostField Value
RemainingDuration
The time that is required to complete the unfinished part of a task.
public static readonly Key<duration, taskkey=""> RemainingDurationField Value
RemainingOvertimeCost
The remaining scheduled overtime expense for a task.
public static readonly Key<decimal, taskkey=""> RemainingOvertimeCostField Value
RemainingOvertimeWork
The amount of remaining scheduled overtime time.
public static readonly Key<duration, taskkey=""> RemainingOvertimeWorkField Value
RemainingWork
The time still required to complete a task or set of tasks.
public static readonly Key<duration, taskkey=""> RemainingWorkField Value
Resume
The date that the remaining part of a task is scheduled to resume after entering any progress.
public static readonly Key<datetime, taskkey=""> ResumeField Value
SV
The earned value schedule variance, through the project status date. Schedule variance (SV) is the difference between the BCWP and the BCWS.
public static readonly Key<double, taskkey=""> SVField Value
Start
The scheduled start date of a task.
public static readonly Key<datetime, taskkey=""> StartField Value
StartSlackTimeSpan
The duration between the Early Start and Late Start dates.
public static readonly Key<timespan, taskkey=""> StartSlackTimeSpanField Value
StartText
Returns the task’s start text.
public static readonly Key<string, taskkey=""> StartTextField Value
StartVariance
The time that represents the difference between a baseline start date of a task or assignment and its currently scheduled start date.
public static readonly Key<duration, taskkey=""> StartVarianceField Value
StatusManager
The name of the enterprise resource who is to receive status updates for the current task from resources.
public static readonly Key<string, taskkey=""> StatusManagerField Value
Stop
The date that represents the end of the actual portion of a task.
public static readonly Key<datetime, taskkey=""> StopField Value
SubprojectName
The source location of a subproject.
public static readonly Key<string, taskkey=""> SubprojectNameField Value
TotalSlackTimeSpan
The time a task’s finish date can be delayed without delaying the project’s finish date.
public static readonly Key<timespan, taskkey=""> TotalSlackTimeSpanField Value
Type
The type of a task.
public static readonly Key<tasktype, taskkey=""> TypeField Value
Uid
The unique Id of a task.
public static readonly Key<int, taskkey=""> UidField Value
WBS
Work breakdown structure (WBS) codes.
public static readonly Key<string, taskkey=""> WBSField Value
WBSLevel
The rightmost WBS level of a task.
public static readonly Key<string, taskkey=""> WBSLevelField Value
Warning
Represents the flag which indicates that task has schedule discrepancies.
public static readonly Key<bool, taskkey=""> WarningField Value
Work
The total time scheduled on a task for all assigned resources.
public static readonly Key<duration, taskkey=""> WorkField Value
WorkVariance
The difference between baseline work of a task and the currently scheduled work.
public static readonly Key<duration, taskkey=""> WorkVarianceField Value
Key < Duration , TaskKey > </duration,></duration,></bool,></string,></string,></int,></tasktype,></timespan,></string,></datetime,></string,></duration,></string,></timespan,></datetime,></double,></datetime,></duration,></duration,></decimal,></duration,></decimal,></duration,></int,></datetime,></datetime,></int,></int,></int,></duration,></decimal,></string,></int,></string,></string,></string,></datetime,></datetime,></duration,></duration,></nullablebool,></nullablebool,></datetime,></datetime,></bool,></nullablebool,></bool,></nullablebool,></nullablebool,></nullablebool,></nullablebool,></nullablebool,></nullablebool,></nullablebool,></bool,></nullablebool,></bool,></nullablebool,></nullablebool,></nullablebool,></nullablebool,></nullablebool,></bool,></nullablebool,></int,></string,></string,></string,></nullablebool,></nullablebool,></string,></timespan,></costaccrualtype,></double,></duration,></string,></timespan,></datetime,></int,></string,></int,></earnedvaluemethodtype,></datetime,></datetime,></duration,></string,></duration,></bool,></nullablebool,></datetime,></datetime,></double,></decimal,></string,></constrainttype,></datetime,></int,></datetime,></datetime,></calendar,></double,></duration,></decimal,></double,></double,></duration,></duration,></datetime,></duration,></duration,></decimal,></datetime,></duration,></decimal,></string,></double,>