Enum DateLabel

Enum DateLabel

Namespace: Aspose.Tasks.Visualization
Assembly: Aspose.Tasks.dll (25.2.0)

Specifies the display format for date and time labels in a timescale.

public enum DateLabel

Fields

DayDdMmYyyy = 256

Example is 19/07/2016.

DayDdd = 19

Examples are Mon, Tue.

DayDddDd = 105

Examples are Mon 30, Tue 1

DayDddMDd = 112

Examples are Mon S 30, Tue O 1

DayDddMmDd = 108

Examples are Mon 9/30, Tue 10/1

DayDddMmDdYy = 52

Examples are Mon 9/30/02, Tue 10/1/02

DayDddMmmDd = 23

Examples are Mon Sep 30, Tue Oct 1

DayDddMmmDdYyy = 22

Examples are Mon Sep 30 ‘02, Tue Oct 1 ‘02

DayDddMmmmDd = 111

Examples are Mon September 30, Tue October 1

DayDddd = 18

Examples are Tuesday, Wednesday.

DayDdi = 119

Examples are Mo, Tu

DayDdiDd = 106

Examples are Mo 30, Tu 1

DayDdiMDd = 113

Examples are Mo S 30, Tu O 1

DayDdiMmDd = 109

Examples are Mo 9/30, Tu 10/1

DayDi = 20

Examples are M, T

DayDiDdNoSpace = 121

Examples are M30, T1

DayDiDdSpace = 107

Examples are M 30, T 1

DayDiMDd = 114

Examples are M S 30, T O 1

DayDiMmDd = 110

Examples are M 9/30, T 10/1

DayFromEndDayDd = 41

Examples are Day 2, Day 1, Day -1, Day -2 from the project end.

DayFromEndDd = 54

Examples are 2, 1, -1, -2

DayFromEndDdd = 53

Examples are D2, D1, D-1, D-2

DayFromStartDayDd = 40

Examples are Day -2, Day -1, Day 1, Day 2 from the project start.

DayFromStartDd = 56

Examples are -2, -1, 1, 2

DayFromStartDdd = 55

Examples are D-2, D-1, D1, D2

DayMDd = 115

Examples are S 30, O 1

DayMmDd = 27

Examples are 9/30, 10/1

DayMmDdYy = 26

Examples are 9/30/02, 10/1/02

DayMmmDd = 25

Examples are Sep 30, Oct 1

DayMmmDdYyy = 24

Examples are Sep 30 ‘02, Oct 10 ‘02

DayOfMonthDd = 21

Examples are 30, 1

DayOfYearDd = 118

Examples are 77, 78

DayOfYearDdYyy = 116

Examples are 77 ‘10, 78 ‘10

DayOfYearDdYyyy = 117

Examples are 77 2010, 78 2010

HalfYearFromEndH = 135

Examples are 2, 1, -1, -2. Half years from the project end date.

HalfYearFromEndHalfH = 133

Examples are Half 2, Half 1, Half -1, Half -2

HalfYearFromEndHh = 134

Examples are H2, H1, H-1, H-2

HalfYearFromStartH = 132

Examples are -2, -1, 1, 2. Half years from the project start date.

HalfYearFromStartHalfH = 130

Examples are Half -2, Half -1, Half 1, Half 2

HalfYearFromStartHh = 131

Examples are H-2, H-1, H1, H2

HalfYearH = 128

Examples are 1, 2. Requires the time unit to be TimescaleHalfYears.

HalfYearHHyy = 129

Examples are 1H10, 2H10

HalfYearHh = 127

Examples are H1, H2

HalfYearHhYyy = 126

Examples are H1 ‘10, H2 ‘10

HalfYearHhhHalf = 123

Examples are 1st Half, 2d Half

HalfYearHlfH = 125

Examples are Half 1, Half 2

HalfYearHlfHYyyy = 124

Examples are Half 1, 2010; Half 2, 2010

HourDddMmmDdHhAm = 28

Examples are Wed Mar 18, 8 AM; Wed Mar 18, 9 AM. Requires the time unit to be TimescaleHours.

HourFromEndHh = 77

Examples are 3, 2, 1, -1, -2 hours from the project end.

HourFromEndHhh = 76

Examples are H3, H2, H1, H-1, H-2

HourFromEndHourHh = 39

Examples are Hour 3, Hour 2, Hour 1, Hour -1, Hour -2

HourFromStartHh = 79

Examples are -2, -1, 1, 2, 3 hours from the project start.

HourFromStartHhh = 78

Examples are H-2, H-1, H1, H2, H3

HourFromStartHourHh = 38

Examples are Hour -2, Hour -1, Hour 1, Hour 2, Hour 3

HourHh = 32

Examples are 8, 9, 10, 11

HourHhAm = 31

Examples are 8AM, 9AM

HourHhMmAm = 30

Examples are 8:00 AM, 9:00 AM

HourMmDdHhAm = 120

Examples are 3/18 8 AM, 3/18 9 AM

HourMmmDdHhAm = 29

Examples are Mar 18, 8 AM; Mar 18, 9 AM

MinuteFromEndMinuteMm = 37

Examples are Minute 181, Minute 180, …, Minute 1, Minute -1 from the project end.

MinuteFromEndMm = 81

Examples are 181, 180, …, 1, -1

MinuteFromEndMmm = 80

Examples are M181, M180, …, M1, M-1

MinuteFromStartMinuteMm = 36

Examples are Minute -2, Minute -1, Minute 1, … Minute 180 from the project start.

MinuteFromStartMm = 83

Examples are -2, -1, 1, …, 180

MinuteFromStartMmm = 82

Examples are M-2, M-1, M1, …, M180

MinuteHhMmAm = 33

Examples are 8:00 AM, 8:01 AM, 8:02 AM. Requires the time unit to be TimescaleMinutes.

MinuteMm = 34

Examples are 0, 1, 2, …, 59 minutes

MonthFromEndMm = 59

Examples are 2, 1, -1, -2 months from the project end.

MonthFromEndMmm = 58

Examples are M2, M1, M-1, M-2

MonthFromEndMonthMm = 45

Examples are Month 2, Month 1, Month -1, Month -2

MonthFromStartMm = 61

Examples are -2, -2, 1, 2 months from the project start.

MonthFromStartMmm = 60

Examples are M-2, M-1, M1, M2

MonthFromStartMonthMm = 44

Examples are Month -2, Month -1, Month 1, Month 2

MonthM = 11

Examples are M, A, M, J, J. Requires the time unit to be TimescaleMonths.

MonthMm = 57

Examples are 11, 12, 1, 2

MonthMmYy = 86

Examples are 3/10, 4/10, 5/10

MonthMmYyy = 85

Examples are 3 ‘10, 4 ‘10, 5 ‘10

MonthMmm = 10

Examples are Mar, Apr, May

MonthMmmYyy = 8

Examples are Mar ‘10, Apr ‘10, May ‘10

MonthMmmm = 9

Examples are March, April, May

MonthMmmmYyyy = 7

Examples are March 2010, April 2010, May 2010

None = 35

No date is displayed.

QuarterFromEndQ = 64

Examples are 5, 4, 3, 2, 1, -1 quarters from the project end.

QuarterFromEndQq = 63

Examples are Q5, Q4, Q3, Q2, Q1, Q-1

QuarterFromEndQuarterQ = 47

Examples are Quarter 5, Quarter 4, Quarter 3, Quarter 2, Quarter 1, Quarter -1

QuarterFromStartQ = 66

Examples are -5, -4, -3, -2, -1, 1 quarters from the project start.

QuarterFromStartQq = 65

Examples are Q-5, Q-4, Q-3, Q-2, Q-1, Q1

QuarterFromStartQuarterQ = 46

Examples are Quarter -5, Quarter -4, Quarter -3, Quarter -2, Quarter -1, Quarter 1

QuarterQ = 62

Examples are 3, 4, 1. Requires the time unit to be TimescaleQuarters.

QuarterQQyy = 51

Examples are 3Q10, 4Q10, 1Q11

QuarterQq = 6

Examples are Q3, Q4, Q1

QuarterQqYyy = 4

Examples are Q3 ‘10, Q4 ‘10, Q1 ‘11

QuarterQqqQuarter = 2

Examples are 3rd Quarter, 1st Quarter

QuarterQtrQ = 5

Examples are Qtr3, Qtr4, Qtr1

QuarterQtrQYyyy = 3

Examples are Qtr3, 2010; Qtr4, 2010; Qtr1, 2011

ThirdsOfMonthsDd = 136

Examples are 1, 11, 21, 1. Requires the time unit to be TimescaleThirdsOfMonths.

ThirdsOfMonthsDdd = 137

Examples are B, M, E, B

ThirdsOfMonthsDddd = 138

Examples are Beginning, Middle, End, Beginning

ThirdsOfMonthsMmDd = 139

Example is 3/1.

ThirdsOfMonthsMmDdYy = 145

Example is 3/1/10.

ThirdsOfMonthsMmDdd = 140

Examples are 3/B, 3/M, 3/E, 4/B

ThirdsOfMonthsMmDddYy = 146

Example is 3/B/10.

ThirdsOfMonthsMmmDd = 142

Examples are Mar 1, Mar 11, Mar 21, Apr 1

ThirdsOfMonthsMmmDdYy = 147

Examples are Mar 1, ‘10; Mar 11, ‘10; Mar 21, ‘10; Apr 1, 10

ThirdsOfMonthsMmmDdd = 143

Examples are Mar B, Mar M, Mar E, Apr B

ThirdsOfMonthsMmmDddYy = 148

Examples are Mar B, ‘10; Mar M, ‘10; Mar E, ‘10; Apr B ‘10

ThirdsOfMonthsMmmmDd = 144

Examples are March 1, March 11, March 21, April 1

ThirdsOfMonthsMmmmDdYyyy = 149

Examples are March 1, 2010; March 11, 2010; March 21, 2010; April 1, 2010

ThirdsOfMonthsMmmmDddd = 141

Examples are March Beginning, March Middle, March End, April Beginning

ThirdsOfMonthsMmmmDdddYyyy = 150

Examples are March Beginning, 2010; March Middle, 2010; March End, 2010; April Beginning, 2010

WeekDayOfMonthDd = 87

Examples are 21, 28, 4

WeekDddDd = 88

Examples are Sun 21, Sun 28, Sun 4. Requires the time unit to be TimescaleWeeks.

WeekDddMDd = 97

Examples are Sun M 21, Sun M 28, Sun A 4

WeekDddMmDd = 90

Examples are Sun 3/21, Sun 3/28, Sun 4/4

WeekDddMmDdYy = 100

Examples are Sun 3/21/10, Sun 3/28/10, Sun 4/4/10

WeekDddMmmDd = 93

Examples are Sun Mar 21, Sun Mar 28, Sun Apr 4

WeekDddMmmDdYyy = 101

Examples are Sun Mar 21, ‘10; Sun Mar 28, ‘10; Sun Apr 4, ‘10

WeekDddMmmmDd = 96

Examples are Sun Mar 21, Sun March 28, Sun Apr 4

WeekDddMmmmDdYyy = 102

Examples are Sun March 21, ‘10; Sun March 28, ‘10; Sun April 4, ‘10

WeekDddWw = 103

Examples are Sun 12, Sun 13, Sun 14

WeekDdiMDd = 98

Examples are Su M 21, Su M 28, Su A 4

WeekDdiMmDd = 91

Examples are Su 3/21. Su 3/28, Su 4/4

WeekDdiMmmDd = 94

Examples are Su Mar 21, Su Mar 28, Su Apr 4

WeekDiMDd = 99

Examples are S M 21, S M 28, S A 4

WeekDiMmDd = 92

Examples are S 3/21, S 3/28, S 4/4

WeekDiMmmDd = 95

Examples are S Mar 21, S Mar 28, S Apr 4

WeekFromEndWeekWw = 43

Examples are Week 2, Week 1, Week -1 from the project end.

WeekFromEndWw = 68

Examples are 2, 1, -1

WeekFromEndWww = 67

Examples are W2, W1, W-1

WeekFromStartWeekWw = 42

Examples are Week -1, Week 1, Week 2 from the project start.

WeekFromStartWw = 70

Examples are -1, 1, 2

WeekFromStartWww = 69

Examples are W-1, W1, W2

WeekMDd = 89

Examples are M21, M28, A 4

WeekMmDd = 17

Examples are 3/21, 3/28, 4/4

WeekMmDdYy = 16

Example is ‘3/21/10’.

WeekMmmDd = 15

Examples are Mar 21, Mar 28, Apr 4

WeekMmmDdYyy = 13

Examples are Mar 21, ‘10; Mar 28, ‘10; Apr 4, ‘10

WeekMmmmDd = 14

Examples are March 21, March 28, April 4

WeekMmmmDdYyyy = 12

Examples are March 21, 2010; March 28, 2010; April 4, 2010

WeekNumberDdWw = 104

Examples are 1 12, 1 13, 1 14 (day 1 of week 12, day 1 of week 13, and so forth)

WeekNumberWw = 50

Examples are 12, 13, 14

YearFromEndYearYy = 49

Examples are Year 2, Year 1, Year -1 from the project end.

YearFromEndYy = 72

Examples are 2, 1, -1

YearFromEndYyy = 71

Examples are Y2, Y1, Y-1

YearFromStartYearYy = 48

Examples are Year -1, Year 1, Year 2 from the project start.

YearFromStartYy = 74

Examples are -1, 1, 2

YearFromStartYyy = 73

Examples are Y-1, Y1, Y2

YearYy = 75

Examples are 10, 11, 12. Requires the time unit to be TimescaleYears.

YearYyy = 1

Examples are ‘10, ‘11, ‘12

YearYyyy = 0

Examples are 2010, 2011, 2012